Events on Arklow Bank - phase 2

Ireland
Consent Application Submitted
800MW Capacity
4C Offshore | Location Map: Lat(52.798) Lon(-5.948)

Events overview for Arklow Bank - phase 2

Event Date Event Type Event

Description

Event Source
Subscribers Only Subscribers Only

Event Date: Subscribers Only

Event Type: Subscribers Only

Subscribers Only

Subscribers Only
Explorer Insights Only 2028 Generating Power

Event Date: Explorer Insights Only 2028

Event Type: Generating Power

Update December 2022: SSE has stated that it aims ... Subscribers Only

Subscribers Only
Explorer Insights Only 2027 Offshore Construction Starts

Event Date: Explorer Insights Only 2027

Event Type: Offshore Construction Starts

Update May 2023: 4C has added a 12 month delay to ... Subscribers Only

Subscribers Only
Explorer Insights Only 2026 Onshore Construction Starts

Event Date: Explorer Insights Only 2026

Event Type: Onshore Construction Starts

Update March 2022: Project has been up scaled and... Subscribers Only

Subscribers Only
Explorer Insights Only 2026 Financial Close

Event Date: Explorer Insights Only 2026

Event Type: Financial Close

Update March 2022: The up scaled offshore wind ene... Subscribers Only

Subscribers Only
Explorer Insights Only 2025 Site Exclusivity Revoked/Expired

Event Date: Explorer Insights Only 2025

Event Type: Site Exclusivity Revoked/Expired

The developer must find a route to market on or be... Subscribers Only

Subscribers Only
Explorer Insights Only 2025 Consent Authorised

Event Date: Explorer Insights Only 2025

Event Type: Consent Authorised

SSE could receive planning consent in 2025 assumin... Subscribers Only

Subscribers Only
Explorer Insights Only 2024 Consent Application Submitted

Event Date: Explorer Insights Only 2024

Event Type: Consent Application Submitted

Update 6th June: SSE (Sure Partners Ltd) have subm... Subscribers Only

Subscribers Only
Explorer Insights Only 2024 Met Mast/LiDAR

Event Date: Explorer Insights Only 2024

Event Type: Met Mast/LiDAR

Removal of floating LiDAR used for wind resource s... Subscribers Only

Subscribers Only
Explorer Insights Only 2023 Site Investigation

Event Date: Explorer Insights Only 2023

Event Type: Site Investigation

Survey vessel Connector started a geotecnical surv... Subscribers Only

Subscribers Only
Explorer Insights Only 2023 Offtake/Site Tender or Process

Event Date: Explorer Insights Only 2023

Event Type: Offtake/Site Tender or Process

Update 11 May 2023: SSE was unsuccessful in ORESS ... Subscribers Only

Subscribers Only
Explorer Insights Only 2023 Consultation

Event Date: Explorer Insights Only 2023

Event Type: Consultation

Public consultation on the project opened. The pub... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Grid Connection Other

Event Date: Explorer Insights Only 2022

Event Type: Grid Connection Other

The project is set to receive a grid Connection As... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Site Exclusivity

Event Date: Explorer Insights Only 2022

Event Type: Site Exclusivity

Sure Partners Limited was awarded site exclusivity... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Site Investigation

Event Date: Explorer Insights Only 2022

Event Type: Site Investigation

A geophysical site survey campaign started. The wo... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Site Investigation

Event Date: Explorer Insights Only 2022

Event Type: Site Investigation

The offshore investigation works took place over a... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Other Application Submitted

Event Date: Explorer Insights Only 2022

Event Type: Other Application Submitted

The developer, SSE, stated that it had submitted a... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Site Investigation

Event Date: Explorer Insights Only 2022

Event Type: Site Investigation

Update 03/08/22 The Vessel Neptune completed its s... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Grid Connection Other

Event Date: Explorer Insights Only 2022

Event Type: Grid Connection Other

An Bord Pleanála (planning authority in Ireland) g... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Site Investigation

Event Date: Explorer Insights Only 2022

Event Type: Site Investigation

Nearshore landfall Site Investigation were due to ... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Site Investigation

Event Date: Explorer Insights Only 2022

Event Type: Site Investigation

Array Area Site Investigation will take place wit... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Met Mast/LiDAR

Event Date: Explorer Insights Only 2022

Event Type: Met Mast/LiDAR

Floating LiDAR Deployment was scheduled to take pl... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Other

Event Date: Explorer Insights Only 2022

Event Type: Other

SSE Renewables confirmed its intention to apply fo... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2022

Event Type: Procurement Process (Supply Chain)

SSE Renewables launched a tender for the supply, f... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2022

Event Type: Procurement Process (Supply Chain)

The project developer, Sure Partners, issued a ten... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2022

Event Type: Procurement Process (Supply Chain)

SSE Renewables is tendering for Marine Substructur... Subscribers Only

Subscribers Only
Explorer Insights Only 2022 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2022

Event Type: Procurement Process (Supply Chain)

SSE renewables announced a tender for supply, inst... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Offtake/Site Tender or Process

Event Date: Explorer Insights Only 2021

Event Type: Offtake/Site Tender or Process

According to the Climate Action Plan, published Ju... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Geotechnical Site Investigation

Event Date: Explorer Insights Only 2021

Event Type: Geotechnical Site Investigation

SSE planned for geotechnical investigations to beg... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Other Approval

Event Date: Explorer Insights Only 2021

Event Type: Other Approval

Update 11 June 2021: SSE Renewables submitted a re... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Grid Connection Other

Event Date: Explorer Insights Only 2021

Event Type: Grid Connection Other

Update 26 June 2021: SSE Renewables has submitted ... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Other Approval

Event Date: Explorer Insights Only 2021

Event Type: Other Approval

SSE Renewables held a consultation for Arklow Ban... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Consultation

Event Date: Explorer Insights Only 2021

Event Type: Consultation

Public consultation started for a state of the art... Subscribers Only

Subscribers Only
Explorer Insights Only 2021 Other Application Submitted

Event Date: Explorer Insights Only 2021

Event Type: Other Application Submitted

SSE ran a public consultation from 7 June 2021 to ... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Other Application Submitted

Event Date: Explorer Insights Only 2020

Event Type: Other Application Submitted

The pre-application consultation request for onsho... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Consultation

Event Date: Explorer Insights Only 2020

Event Type: Consultation

SSE Renewables has issued two periodic indicative ... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2020

Event Type: Procurement Process (Supply Chain)

SSE initiated a Preliminary Market Consultation (P... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Consultation

Event Date: Explorer Insights Only 2020

Event Type: Consultation

The first public consultation (virtual because of ... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Geotechnical Site Investigation

Event Date: Explorer Insights Only 2020

Event Type: Geotechnical Site Investigation

Update: vessel arrived on site.

Weather dependi... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Other Approval

Event Date: Explorer Insights Only 2020

Event Type: Other Approval

The foreshore licence was granted with the standar... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2020

Event Type: Procurement Process (Supply Chain)

SSE tendered for an offshore WTG substructure FEED... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Other

Event Date: Explorer Insights Only 2020

Event Type: Other

The project EIA scoping report was published. It w... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Met Mast/LiDAR

Event Date: Explorer Insights Only 2020

Event Type: Met Mast/LiDAR

Update: vessels arrived 23rd August 2020.

Updat... Subscribers Only

Subscribers Only
Explorer Insights Only 2020 Consultation

Event Date: Explorer Insights Only 2020

Event Type: Consultation

Update: due to impacts of COVID-19 the consultatio... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Met Mast/LiDAR

Event Date: Explorer Insights Only 2019

Event Type: Met Mast/LiDAR

Five metocean buoys were deployed in late October/... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2019

Event Type: Procurement Process (Supply Chain)

SSE issued a tender for provision of a floating li... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Geotechnical Site Investigation

Event Date: Explorer Insights Only 2019

Event Type: Geotechnical Site Investigation

Geotechnical vessel, Fugro Excalibur arrived on si... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Other Application Submitted

Event Date: Explorer Insights Only 2019

Event Type: Other Application Submitted

SSE submitted a foreshore licence application in o... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Other

Event Date: Explorer Insights Only 2019

Event Type: Other

Arklow Bank Wind Park was awaiting details regard... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Site Investigation

Event Date: Explorer Insights Only 2019

Event Type: Site Investigation

Two vessels, the AMS Panther and the AMS Retriever... Subscribers Only

Subscribers Only
Explorer Insights Only 2019 Other

Event Date: Explorer Insights Only 2019

Event Type: Other

Site assessment of local ports - Arklow Harbour an... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2018

Event Type: Procurement Process (Supply Chain)

SSE announced a tender for provision of offshore a... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Other

Event Date: Explorer Insights Only 2018

Event Type: Other

SSE announced a tender for provision of electrical... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Other

Event Date: Explorer Insights Only 2018

Event Type: Other

Update: the survey was cancelled due to challengin... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Other

Event Date: Explorer Insights Only 2018

Event Type: Other

SSE proposed to invest €1-2bn in CAPEX to develop ... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Other

Event Date: Explorer Insights Only 2018

Event Type: Other

SSE gave a presentation at a County Wicklow Counci... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2018

Event Type: Procurement Process (Supply Chain)

SSE announced a tender for provision of up to two ... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Procurement Process (Supply Chain)

Event Date: Explorer Insights Only 2018

Event Type: Procurement Process (Supply Chain)

Tender for the provision of offshore and near shor... Subscribers Only

Subscribers Only
Explorer Insights Only 2018 Other

Event Date: Explorer Insights Only 2018

Event Type: Other

At the Joint Committee on Communications, Climate ... Subscribers Only

Subscribers Only
Explorer Insights Only 2017 Other

Event Date: Explorer Insights Only 2017

Event Type: Other

The Electricity Supply Board (ESB), majority owned... Subscribers Only

Subscribers Only
Explorer Insights Only 2017 Other

Event Date: Explorer Insights Only 2017

Event Type: Other

In September 2017 the Irish Government published a... Subscribers Only

Subscribers Only
Explorer Insights Only 2016 Strategy or Policy Development

Event Date: Explorer Insights Only 2016

Event Type: Strategy or Policy Development

Update September 2016:
PA memorandum of understa... Subscribers Only

Subscribers Only
Explorer Insights Only 2014 Other

Event Date: Explorer Insights Only 2014

Event Type: Other

Update August 2014: DECC published a notice: Contr... Subscribers Only

Subscribers Only
Explorer Insights Only 2014 Other

Event Date: Explorer Insights Only 2014

Event Type: Other

In March 2014 the talks continued to drag on but i... Subscribers Only

Subscribers Only
Explorer Insights Only 2013 Other

Event Date: Explorer Insights Only 2013

Event Type: Other

In October 2013 Pat Rabbitte (former Minister for ... Subscribers Only

Subscribers Only
Explorer Insights Only 2013 Other

Event Date: Explorer Insights Only 2013

Event Type: Other

On 24th January 2013 the Irish Energy Minister Pat... Subscribers Only

Subscribers Only
Explorer Insights Only 2012 Other

Event Date: Explorer Insights Only 2012

Event Type: Other

In January 2012, as stated in the first report on ... Subscribers Only

Subscribers Only
Explorer Insights Only 2002 Other Approval

Event Date: Explorer Insights Only 2002

Event Type: Other Approval

Foreshore Lease Secured to develop 520 MW of offsh... Subscribers Only

Subscribers Only

How does the database work?

4C Offshore marine intelligence software provides you with exclusive access to a range of specialised services including the Global Offshore Wind Farm Database. 4C Offshore grants you exclusive access to online and offline databases, reports, newsletters, online tools and more.

There are three levels of access: Free, Explorer Insights and Full. Explorer Insights allows you to personalise notifications, use the search function and access more data.

You will need Full access to use the 4C Offshore interactive system, access reports, updates, news, downloads and more. To find out more about how 4C Offshore software works and the benefits of Full access, enquire below.

Free account registration

Register today at no cost to our Explorer Insights subscription and access more of the 4C Offshore database and additional functionality such as tailored notifications, enhanced search capabilities.

Understand the market and make better decisions with access to the entire 4C Offshore database through our Premium subscription, providing crucial marketing intelligence across all major segments of the offshore renewable energy sector.

Premium users have unlimited access to a comprehensive dashboard of options via our dedicated web app with exclusive access to online and offline databases, analysis, reports, webinars, newsletters, interactive online tools, maps and more. Enquire today by selecting the “Premium” tab above.

Account Usage
Main Interest
I have read the privacy policy. and agree to the terms of service.

Ask us about our premium subscription

Gain access to the 4C Offshore web app and dashboard, the powerful intelligence tool fueled by TGS offshore global wind market data and insights.

Full, unlimited access to exclusive offshore data and insight to fuel your wind development decisions.

Discover insights through detailed graphs and charts to help you calculate market shares and explore ownership stakes and costs.

Main Interest
I have read the privacy policy. and agree to the terms of service.